Union Station Neighborhood - Project Roadmap
Complete: Community Visioning & Concept Selection
Initial planning studies (Make Ogden, Union Station Framework, Ogden Onboard, etc.)
Broad community engagement sessions (2020–2024)
Selection of preferred concept (“Concept C”)
In Progress (Live): Detailed Master Plan Development
Consultant team preparing site plans, land use framework, circulation, open space, and design standards
Ongoing public open houses & workshops
Integration of museum, transit, Wall Avenue, and economic study component
Planned | Upcoming: Draft Master Plan Finalization
Incorporate public feedback into refined plan
Technical review (city departments, UTA, UDOT, consultants)
Produce complete draft for Council/Planning Commission
Planned | Upcoming: Formal Public Review & Adoption
Planning Commission hearings
City Council hearings
Public communications and publishing final plan
Formal Adoption of Union Station Neighborhood Master Plan
Planned | Upcoming: Implementation Tools & Approvals
Update zoning & overlays (if needed)
Adopt design guidelines/standards
Establish/amend Funding or other related boundaries
Finalize financing strategies (RDA/TIF/HTRZ, bonds, grants)
Planned | Upcoming: Exclusive Negotiation Agreement → Master Development Agreement
Transition from ENA to executed MDA with development partner
Define roles, phasing, and funding commitments
Formalize responsibilities between City, UTA, private developer, and museum partners
Planned | Upcoming: Pre-Development & Site Preparation
Utility coordination (water, sewer, power, telecom)
Environmental review/remediation (if needed on former UP/UTA parcels)
Demolition of non-historic/temporary structures
Interim site uses (parking, staging) planned during transition
Planned | Upcoming: Infrastructure & Public Realm Construction (Phase 1)
Wall Avenue reconstruction & streetscape
Transit/parking structure buildout
Union Station Plaza and pedestrian connections
Streets, sidewalks, lighting, and utilities installed
Planned | Upcoming: Vertical Development (Phase 2+)
Mixed-use parcels (north and south sites) activated with private development
Ground floors: retail/restaurant/office
Upper floors: residential, hospitality, office
Ongoing buildout of plazas, paseos, open space
Planned | Upcoming: Project Delivery & Monitoring
Ongoing phasing over multiple years
Periodic updates to Master Plan as conditions change
Continued engagement through Union Station Neighborhood Engagement Group
Museum planning - New Facility + Union Station Restoration
Complete: Collections Study & Visioning
Review of existing Union Station collections (railroad, firearms, classic cars, etc.)
Space needs analysis and initial curatorial direction
Vision for a new facility to house collections and enable full historic restoration of Union Station
In Progress (Live): Concept Design (Current Phase)
Consultant team developing concept layouts for new museum building adjacent to Union Station
Integration of exhibit zones, collection storage, archives, education spaces, and visitor services
Coordination with Union Station restoration needs and public plaza design
Initial public open house presentation (October 2025)
Planned | Upcoming: Funding & Fundraising Strategy
Develop capital campaign (local philanthropy, state/federal cultural grants, foundation partners)
Identify private donors and naming opportunities
Establish project governance structure (City + Museum partners + fundraising foundation)
Launch phased fundraising campaign with public/private targets
Planned | Upcoming: Schematic Design
Translate concept plans into building diagrams (floor plans, elevations, site layout)
Address adjacencies for exhibits, loading, visitor circulation, and plaza connection
Cost estimating and refinement to match fundraising capacity
Planned | Upcoming: Design Development
Detailed architectural drawings (materials, systems, sustainability features)
Coordination with UDOT (Wall Avenue) and UTA (transit plaza) designs
Begin preliminary permitting discussions with City departments
Planned | Upcoming: Construction Documents
Complete stamped architectural and engineering plans
Formal permitting (building, fire, accessibility, environmental reviews)
Bid package prepared for contractor procurement
Planned | Upcoming: Procurement & Contracting
Competitive bid/RFP for general contractor (or CM/GC approach)
Contract execution, guaranteed maximum price (GMP) negotiated
Pre-construction services (schedule, logistics, safety, phasing with Union Station operations)
Planned | Upcoming: Construction Phase
Site preparation and utility relocation
Building foundation, shell, and core
Interiors: galleries, archives, classrooms, offices, event spaces
Exterior plaza connections and landscaping
Concurrent Union Station restoration (historic Great Hall, wings, Laundry Building)
Planned | Upcoming: Exhibit Fabrication & Installation
Curatorial team finalizes exhibit narratives and design
Fabricators build and install interactive displays, signage, lighting, and casework
Move of collections from Union Station to new facility (with conservation protocols)
Planned | Upcoming: Opening Preparation
Staff training, soft openings, community preview events
Marketing and tourism partnerships launched (Visit Ogden, UTA, etc.)
Grand opening event and ribbon cutting
Planned | Upcoming: Ongoing Operations & Programming
Rotate exhibits to maintain freshness and relevance
Educational programming with Weber State, schools, and cultural groups
Continued fundraising for endowment and long-term sustainability
Transit Planning - Restoring Union Station as a Regional Hub
Complete: Union Station Identified as Transit Hub
Ogden City + Utah Transit Authority (UTA) agreement to plan jointly for Union Station’s role as a transit hub
Union Station identified in Ogden Onboard and Union Station Framework as preferred future location for Frontrunner and bus service integration
In Progress (Live): Coordination on Service Integration (Current Phase)
Planning with UTA to relocate Frontrunner platform adjacent to Union Station
Planning the integration of BRT (Bus Rapid Transit), local bus routes, and pedestrian/bike access
Coordination with UDOT Wall Avenue redesign to ensure connectivity
In Progress (Live): Feasibility & Engineering Studies
Evaluate track realignment and platform design options
Assess impacts to existing bus loop, parking, and BRT alignment
Define passenger circulation (entries, ticketing, waiting, pedestrian pathways)
Prepare cost estimates and phasing plan for construction
Planned | Upcoming: Funding Commitments & Environmental Review
Secure federal/state capital funding (FTA, UDOT, Legislature)
Identify local match sources (RDA, sales tax, bonding, CRA tools)
Complete environmental review (NEPA/FTA compliance)
Conduct public hearings for transit design and environmental clearances
Planned | Upcoming: Preliminary & Final Engineering
Preliminary engineering: refine alignment, station footprint, utilities, and structural design
Final engineering: complete stamped construction documents
Coordinate design with Union Station Plaza, museum, and Wall Avenue projects
Obtain permits and final approvals
Planned | Upcoming: Construction of Transit Facilities
Site prep and utility relocation
Build new Frontrunner platform and canopies at Union Station
Construct bus bays, BRT stops, and pedestrian plaza connections
Install wayfinding, lighting, safety features, and parking access improvements
Maintain transit operations during phased construction
Planned | Upcoming: Return of Frontrunner Service to Union Station
Testing and safety certification of new station and rail facilities
Launch of integrated transit services: Frontrunner directly serving Union Station, BRT and bus routes connecting seamlessly at new transit plaza, Pedestrian and bike links to downtown and regional trails
Public opening ceremony marking the return of passenger rail to Union Station